Project Description
CATA pipeline replacement
Replacement of CATA Dam pipeline
Project description
Calliper was appointed to do the planning and implementation for the replacement of a portion of the CATA Dam pipeline and the realignment of the existing pipeline.
Project objectives
- New pipeline to replace the existing pipeline, which had reached the end of its useful life and suffered numerous pipe failures resulting in supply interruptions to some units of the irrigation scheme
- Work done ensured a reliable bulk water supply to the Keiskammahoek irrigation scheme
Project Details
CONSTRUCTION PERIOD
36 months
CLIENT
Department of Water and Sanitation
PROJECT TYPE
PROJECT LOCATION
Near the Keiskammahoek Irrigation Scheme in the town of Keiskammahoek in the Eastern Cape
SERVICES RENDERED
- Structural Engineering
- Civil Design and Engineering
- Project Management
- Occupational Health and Safety
- Environmental Management Services
- Water and Sanitation
- Topographic Surveys
- Geotechnical Engineering