Project description
Calliper was appointed to provide engineering input to the high-level assessment of the Brakpan/Withok tailings complex of DRD Gold. The scope included the review of available design or as-built drawings, visual assessment of site infrastructure with reference to available drawings, compilation of a report with findings and recommendations. Calliper also provided costs for engineering works required to achieve the stormwater management plan.
Project objectives
- To determine surface water compliance
- To determine stability and overall safety of the tailings complex and associated infrastructure
Project Details
CONSTRUCTION PERIOD
1 month
CLIENT
Highlands Hydrology
PROJECT TYPE
PROJECT LOCATION
Brakpan/Withok